- #1
LiHJ
- 43
- 2
Homework Statement
Dear Helpers,
This is the question:
It takes 30 days for 6 trained workers to complete a painting job. The same painting job can also be completed in 30 days by a group of 10 untrained workers. How long would a group of 4 untrained and 4 trained workers to complete the same painting job?
Homework Equations
The Attempt at a Solution
This is my working:
Rate of working based on 30 days (Trained)= (1/6)
Rate of working based on 30 days (Trained)= (1/10)
Combined rate of working based on 30 days = (1/6)+(1/10)=(4/15)
Amount of work done by 4 set of (1 Untrained + 1 trained) workers express in fraction=
(4/15) x 4=(16/15)
(16/15) -----30days
1 whole ------ 30 x (15/16)=28.125
therefore answer = 29 days
Is my working logical or can be better?
Thank you