- #1
paulmdrdo1
- 385
- 0
1. Metallurgy. How much pure gold should be melted with
15 grams of 14-karat gold to produce 18-karat gold?
2. Road Construction. A new machine that deposits cement
for a road requires 12 hours to complete a one-half mile section of road. An older machine requires 16 hours to pave the same amount of road. After depositing cement for 4 hours, the new machine develops a mechanical problem and quits working. The older machine is brought into place and continues the job. How long does it take the older machine to complete the job?
my attempt on 1st problem
x = amount of pure gold
$15\frac{14}{24}+x=\frac{18}{24}(15+x)$
x = 10 grams
for 2nd I get the correct answer but I'm not sure If I modeled the situation correctly.
$\frac{0.5}{12}\cdot 4+\frac{0.5}{16}\cdot x=0.5$
x = 10 and 2/3 hr.
can you give me a more straight forward method for problem 1 and 2. just for variety-of-method's sake.
thanks!
15 grams of 14-karat gold to produce 18-karat gold?
2. Road Construction. A new machine that deposits cement
for a road requires 12 hours to complete a one-half mile section of road. An older machine requires 16 hours to pave the same amount of road. After depositing cement for 4 hours, the new machine develops a mechanical problem and quits working. The older machine is brought into place and continues the job. How long does it take the older machine to complete the job?
my attempt on 1st problem
x = amount of pure gold
$15\frac{14}{24}+x=\frac{18}{24}(15+x)$
x = 10 grams
for 2nd I get the correct answer but I'm not sure If I modeled the situation correctly.
$\frac{0.5}{12}\cdot 4+\frac{0.5}{16}\cdot x=0.5$
x = 10 and 2/3 hr.
can you give me a more straight forward method for problem 1 and 2. just for variety-of-method's sake.
thanks!
Last edited: