Optimize Work and Time Equations: Formula for Calculating Completion Time"

  • Thread starter GlassBones
  • Start date
  • Tags
    Time Work
In summary, A takes 20 days to have 80% completion. Simple algebra gets that A takes 25 days to complete finish by themselves. Now I'm trying to come up with a formula. I came up with this formula. A takes 20 days to have 80% completion. Simple algebra gets that A takes 25 days to complete finish by themselves. Now I'm trying to come up with a formula for how long it will take B, who is working with A, to complete the 20% of the whole work. The sum should be 1/23, ie:A takes 20 days to have 80% completion. Simple algebra gets that A takes 25 days to complete finish by themselves. Now I'm trying to come
  • #1
GlassBones
16
1
Homework Statement
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
Relevant Equations
None
I came up with this formula.

A takes 20 days to have 80% completion. Simple algebra gets that A takes 25 days to complete finish by themselves. Now I'm trying to come up with a formula.

##1/.8(1/25) = 1/20## with 80% completion. Now I'm working with the remaining 20%. ## 1/.2(1/25+1/b)##, where b is the total amount of days B takes to finish 1 work. The sum should be 1/23, ie:

##1/.8(1/25)+1/.2(1/25+1/b) = 1/23##

So I should isolate b to find the number of days B takes to finish alone. In doing so I get a negative number...

What's wrong with my reasoning?
 
Physics news on Phys.org
  • #2
How much work does A do per day as a function of the total work to be done?
 
  • #3
phinds said:
...as a function of the total work to be done

I know A can complete work alone in 25 days. So 1 day A will do 1/25. Is this what your asking? Sorry just confused
 
  • #4
GlassBones said:
I know A can complete work alone in 25 days. So 1 day A will do 1/25. Is this what your asking? Sorry just confused

Right. That's usually what you want to do in these problems, is figure out the fraction per day that each person does.

So A working alone does 1/25 of the job in a day.

Now, given that the team of A + B does 0.20 of a job in 3 days, how much of a job does the team of A + B do in one day?

Do you see what knowing that tells you about B's work output?
 
  • Like
Likes GlassBones
  • #5
GlassBones said:
##1/.8(1/25)+1/.2(1/25+1/b) = 1/23##

So I should isolate b to find the number of days B takes to finish alone. In doing so I get a negative number...

What's wrong with my reasoning?

This does look like it may be doing some of the correct calculations but I can't quite understand your equations.

What does 1/.8 represent? Why are you dividing by the fraction of the job done?

If your first term is equal to 1/20, the reciprocal of the number of days A works, then your second term will be 1/3, the reciprocal of the number of days A + B work together to complete the 0.20 of the job.

But then your equation says (1/20) + (1/3) = (1/23) which is obviously not true.

I think your individual terms on the left are OK, but all you have to do is use the fact that the second term is 1/3. They don't add up to 1/23. And it would be even easier if you worked with the number of days, rather than its reciprocal.
 
  • Like
Likes GlassBones
  • #6
RPinPA said:
But then your equation says (1/20) + (1/3) = (1/23) which is obviously not true.

...yes there's the issue with my reasoning. I can't believe I made this mistake. Thanks everything makes sense
 
  • #7
GlassBones said:
phinds said:
How much work does A do per day as a function of the total work to be done?
I know A can complete work alone in 25 days. So 1 day A will do 1/25. Is this what your asking? Sorry just confused
An alternate way to answer @phinds 's question is:

A can do 4% of a whole work in one day.

Then the question can be answered as follows.

The remaining 20% of a whole work takes A&B 3 days to complete of which A does 3 × 4% = 12%.

So in 3 days B did 8% of a whole work.

Let x be the number of days for B alone to do (100% of) a whole work. Then we have the following proportion.

##\displaystyle \frac{8\%}{100\%}=\frac{3}{x} ##
 
  • #8
You can also compute what percent of the work A has done by the 3rd day and take it from there. B will do the remainder and you can compare the rates.
 

FAQ: Optimize Work and Time Equations: Formula for Calculating Completion Time"

What is the purpose of optimizing work and time equations?

The purpose of optimizing work and time equations is to find the most efficient way to complete a task or project within a given timeframe. It involves finding the balance between the amount of work that needs to be done and the time available to complete it.

What is the formula for calculating completion time?

The formula for calculating completion time is: Completion Time = Work / Rate. This equation takes into account the amount of work that needs to be done and the rate at which it can be completed.

How do you determine the work and rate values for the equation?

The work value can be determined by breaking down the task or project into smaller, manageable chunks and estimating the amount of work required for each. The rate value can be determined by considering factors such as the skills and experience of the individuals working on the task, the availability of resources, and any potential obstacles or delays.

Can this formula be applied to any type of project?

Yes, this formula can be applied to any type of project, whether it is a simple task or a complex project. However, the accuracy of the results may vary depending on the specific circumstances and variables involved in each project.

How can optimizing work and time equations benefit a project?

Optimizing work and time equations can benefit a project in several ways. It can help to improve efficiency and productivity, reduce costs and resources, and ensure that deadlines are met. It can also help to identify potential issues or bottlenecks in the project and allow for adjustments to be made to ensure its successful completion.

Back
Top