- #1
GlassBones
- 16
- 1
- Homework Statement
- A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
- Relevant Equations
- None
I came up with this formula.
A takes 20 days to have 80% completion. Simple algebra gets that A takes 25 days to complete finish by themselves. Now I'm trying to come up with a formula.
##1/.8(1/25) = 1/20## with 80% completion. Now I'm working with the remaining 20%. ## 1/.2(1/25+1/b)##, where b is the total amount of days B takes to finish 1 work. The sum should be 1/23, ie:
##1/.8(1/25)+1/.2(1/25+1/b) = 1/23##
So I should isolate b to find the number of days B takes to finish alone. In doing so I get a negative number...
What's wrong with my reasoning?
A takes 20 days to have 80% completion. Simple algebra gets that A takes 25 days to complete finish by themselves. Now I'm trying to come up with a formula.
##1/.8(1/25) = 1/20## with 80% completion. Now I'm working with the remaining 20%. ## 1/.2(1/25+1/b)##, where b is the total amount of days B takes to finish 1 work. The sum should be 1/23, ie:
##1/.8(1/25)+1/.2(1/25+1/b) = 1/23##
So I should isolate b to find the number of days B takes to finish alone. In doing so I get a negative number...
What's wrong with my reasoning?