Work Rate Problem: 4 Men, 9 Women in 13.388 Days

  • MHB
  • Thread starter NotaMathPerson
  • Start date
  • Tags
    Rate Work
In summary, the problem states that if 18 men or 20 women can do a work in 9 days, in what time can 4 men and 9 men do the same work? Using the given information, we can calculate that the time it takes for 4 men and 9 women to do the same work is approximately 13.388 days. However, the answer provided in the book, $6\frac{1}{20}$ days, does not make sense based on the given information.
  • #1
NotaMathPerson
83
0
If 18 men or 20 women can do a work in 9 days, in what time can 4 men and 9 men do the same work?

My attempt

D = days required

4/162 + 9/180 = 1/D

D = 13.388 days

Is my solution correct?

Thanks!
 
Mathematics news on Phys.org
  • #2
NotaMathPerson said:
If 18 men or 20 women can do a work in 9 days, in what time can 4 men and 9 men do the same work?

My attempt

D = days required

4/162 + 9/180 = 1/D

D = 13.388 days

Is my solution correct?

Thanks!

4 men and 9 men?
 
  • #3
NotaMathPerson said:
If 18 men or 20 women can do a work in 9 days, in what time can 4 men and 9 men do the same work?

My attempt

D = days required

4/162 + 9/180 = 1/D

D = 13.388 days

Is my solution correct?

Thanks!

From your working, I assume the question is actually:

"In what time can 4 men and 9 women do the same work?"

Your method is good, and the solution correct. A single man will take 162 days to complete the work, while a single woman will take 180 days. So, the amount of the job done by each man in a day is 1/162 and for a woman 1/180, and so with 4 men and 9 woman working, the amount done is:

\(\displaystyle \frac{4}{162}+\frac{9}{180}=\frac{121}{1620}\)

and since this is one day's work, this is equal to 1/D of the work. Hence:

\(\displaystyle D=\frac{1620}{121}\approx13.388\)
 
  • #4
MarkFL said:
From your working, I assume the question is actually:

"In what time can 4 men and 9 women do the same work?"

Your method is good, and the solution correct. A single man will take 162 days to complete the work, while a single woman will take 180 days. So, the amount of the job done by each man in a day is 1/162 and for a woman 1/180, and so with 4 men and 9 woman working, the amount done is:

\(\displaystyle \frac{4}{162}+\frac{9}{180}=\frac{121}{1620}\)

and since this is one day's work, this is equal to 1/D of the work. Hence:

\(\displaystyle D=\frac{1620}{121}\approx13.388\)

Hello!

The answer in my book says it is $6\frac{1}{20}$ days. Why is that?
 
  • #5
NotaMathPerson said:
Hello!

The answer in my book says it is $6\frac{1}{20}$ days. Why is that?

If it takes 18 men 9 days to do the work, does it make any sense that it would take 13 people, 9 of which are women (who take slightly longer to do the work) a smaller amount of time?

Did you give the problem exactly as stated?
 
  • #6
MarkFL said:
If it takes 18 men 9 days to do the work, does it make any sense that it would take 13 people, 9 of which are women (who take slightly longer to do the work) a smaller amount of time?

Did you give the problem exactly as stated?

View attachment 5659

Here is the question from the book. This is from a section of ratio and proportion.
 

Attachments

  • Q7finkelp.128.jpg
    Q7finkelp.128.jpg
    6.5 KB · Views: 75
  • #7
That answer would make sense if it took 11 men 4 days to do the job and 11 women need 11 days to do the job. But as given, the answer supplied with the problem is just wrong. :)
 

FAQ: Work Rate Problem: 4 Men, 9 Women in 13.388 Days

How do you calculate the work rate in this problem?

In this problem, work rate is calculated by dividing the total amount of work by the total number of people and the number of days. This gives us the average amount of work each person needs to complete per day.

What is the total amount of work that needs to be completed?

The total amount of work in this problem is not specified, so we cannot calculate it. We only know the number of men, women, and days, and we can use this information to calculate the work rate.

Is the work rate the same for all the men and women in this problem?

No, the work rate may vary for each person depending on their individual abilities and skills. The work rate is simply an average rate for the group as a whole.

Can this problem be solved using any other method besides calculating the work rate?

Yes, this problem can also be solved using other methods such as using a system of equations or using a work formula. However, calculating the work rate is the most straightforward method for this specific problem.

How can we use the work rate to determine the total time needed to complete the work?

To determine the total time needed to complete the work, we can use the work rate to calculate the amount of work completed in one day by all the men and women combined. Then, we can divide the total amount of work by the amount of work completed in one day to get the total number of days needed to complete the work.

Back
Top