- #1
CalvinandHobbes
- 4
- 3
- TL;DR Summary
- If lift water 9,5m high (initially with a pump till it reaches bend), can I raise the level to which 2nd reservoir is filled by installing a siphon drain inside 1st reservoir and empty reservoir no1?
I have no engineering background so apologies if I'm trying to create alchemy without pumps.
I need to empty 10 000l reservoir 4 times a day into a larger vessel, which is slightly lower, but I first have to cross a 9,5m high barrier (site is located about 15m above sea level)
I gather the siphon will only work to deposit the water lower than the intake. Would it be possible to raise the intake level of reservoir no 1 to the top of a siphon drain (a funnel located inside a larger pipe that is closed 1 end) [explanation is just to clarify what i mean as I don't have the correct terminology], or does it remain at the bottom of lowest point of the pipe)?
Is there a risk that the siphon drain can reduce the flow to much and therefore loose the siphon effect of the total installation and makes it counter productive?
Attach a simple sketch to try and illustrate
I need to empty 10 000l reservoir 4 times a day into a larger vessel, which is slightly lower, but I first have to cross a 9,5m high barrier (site is located about 15m above sea level)
I gather the siphon will only work to deposit the water lower than the intake. Would it be possible to raise the intake level of reservoir no 1 to the top of a siphon drain (a funnel located inside a larger pipe that is closed 1 end) [explanation is just to clarify what i mean as I don't have the correct terminology], or does it remain at the bottom of lowest point of the pipe)?
Is there a risk that the siphon drain can reduce the flow to much and therefore loose the siphon effect of the total installation and makes it counter productive?
Attach a simple sketch to try and illustrate